| Statements such as those made in your circular of 80 October
generally lead to false conclusions and only lead to the result that schedules
which have been based on such calculations of capacity cannot be adhered to and
that construction plans are approved as being practicable which, in actual
fact, can never be carried out. We also wish to object to your intention of
putting a measure into force by your circular of 30 October which is to be
valid as of 1 August that is, three months previously. It is impossible to
conduct business in an orderly manner when regulations are issued with so much
delay. |
| |
Heil Hitler!
[Signed] Illegible |
| |
| [Handwritten] Dr. Schaefer |
| |
| |
| |
TRANSLATION OF DOCUMENT NI-14297 PROSECUTION EXHIBIT
1930 |
| |
| LETTER FROM ANOTHER OF THE SUBSIDIARY CONSTRUCTION FIRMS TO
FARBENS LURANIL CONSTRUCTION COMPANY, 11 NOVEMBER 1944, CONCERNING THE
EVALUATION OF FORCED LABORERS |
| |
| |
[Illegible Stamp] To Luranil-Baugesellschaft m. b. H. Dyhernfurth/Oder
|
|
| |
E. Hegerfeld Industriebau-Gesellschaft m. b. H.
Dyhernfurth/Oder, 11 Nov. 1944 He/We
Re: Evaluation of forced
laborers [Verrechnung von Zwangsarbeitern]
We have received your
circular of 30 October and wish to inform you that the efficiency rates given
by you (skilled inmate laborer, 70 percent compared to German laborers;
unskilled inmate-laborers 50 percent compared to German laborers) are not being
reached on our construction site. We reserve further comment on the above
matter. |
| |
Heil Hitler!
E. Hegerfeld Industriebaugesellschaft m. b.
H. [Signed] Illegible |
| |
| [Handwritten] Dr. Schaefer Zinser |