| Document 39 [PMO file BW 
            30/25, page 8]
 | 
        
          |  | 
        
          | 
 | 
        
          |  | 
        
          | Translation: | 
        
          |  | 
        
          | [illegible] BW 30 and 30a | 
        
          | Correspondence register im. 45269/Kir/Lm | 
        
          | Auschwitz, 25/3/42 | 
        
          | Summary record | 
        
          |  | 
        
          | Subject: | Visit by two representatives of 
            Messrs Topf & Sons. Erfurt Chief Engineers Prüfer and Schulze | 
        
          | Reference: | Telegraphed summons with a view 
            to eliminating the faults in Krematorien II and III at Auschwitz POW 
            Camp [Birkenau] | 
        
          | Place and Date: | Auschwitz Waffen SS and Police 
            Central Construction Management 24/3 and 25/3/1943 | 
        
          |  | 
        
          | Krematorium II 
 Since the three forced 
            drought installations have not given satisfaction in any respect. 
            and even suffered damage after the first real utilization because of 
            too high temperatures, they are to be dismantled at the expense of 
            Messrs Topf & Sons and taken back by that firm. The ZBL [Zentral 
            Bauleitung] counts on the fact that it will suffer no loss of 
            material and that the corresponding quantity of iron will be posted 
            to its credit [this concerns the materials rationing]. The ZBL will 
            take the three electric motors (each of 15 HP) with their 
            connections, switch and starter, provided they have not been damaged 
            by the high temperatures. The hot air supply installation for 
            Leichenkeller I [1] must he eliminated because of this modification, 
            and the materials will be stored by the ZBL (in the Bauhof]. In 
            place of the wooden blower for the air extraction installation of 
            Leichenkeller I [1], a cast iron blower has been chosen. The ZBL 
            will assume the additional cost of the blower housing. For the 5 
            three-muffle furnaces, the coffin [!] charging trolley will be 
            replaced by corpse stretchers: the trolley will be stored by the 
            ZBL. Installation of the Demag goods hoist transport platform will 
            be effected by a Topf fitter.
 
 Krematorium III
 
 In view of the experience with Krematorium II, the 
            forced draught installations planned and delivered will not be 
            installed, but will be stored by the ZBL. (For use in the district 
            heating plant).
 
 [initialled by Bischoff]
 | 
        
          | [signed] Kurt Prufer | 
        
          |  | 
        
          | Distribution: 1 Messrs Topf
 1 Machine store
 2 Files
 1 Register POW camp BW 30
 |